Location: Farringdon, london
GKR are providing full scaffold access to the entire external elevations of both the Sorting and Post Office Buildings for Mace limited. These scaffolds once erected will be fully enclosed by Tufcoat sheeting giving full protection for the Main Contractors works. Our Design Team CDS are liaising daily with the Site Engineers Curtains and Temporary Works Engineers due to tight logistical plans for this live 24 hour operating Royal Mail site.
Scope of Works
9,000m2 of Independent Scaffold wrapped in Tufcoat Sheeting
252m run of Gantry Protection Scaffold
8nr Hoist Towers
46m of Protection Fans
715m3 of Birdcage Scaffolds
101m run of Cantilever Scaffolds
1142m2 of Suspended Scaffolds
101m run of roof support scaffold wrapped in Tufcoat Sheeting